top of page

Selected Assignments 

Evergreen Line

​This  $1.4 billion new addition to the existing Vancouver Skytrain system extends the transit system 11 km through Burnaby and Port Moody into Coquitlam. It adds 7 new stations along it’s route and was completed in 2016.

 

Tim Stanley was the Partner in Charge of the design team responsible for a significant portion of the elevated guideway and several of the stations on behalf of the project’s Design Builder. Tim Stanley also acted as the Project Manager of the Preliminary Design when the line was conceived as an at-grade LRT prior to the decision to utilize the Sky Train technology.

Canada Line

Canada Line was the first Public Private Partnership transit line in Canada. The $2.0 billion project connects Vancouver’s downtown transit hub with the City of Richmond and Vancouver International Airport. The 19.2 km LRT line has 16 stations and runs on a dedicated (tunnel and elevated guideway) alignment. The project was completed ahead of schedule and on budget in 2009.

 

Tim Stanley was the Executive Sponsor of the Owners Engineer team during the design and construction of the project by the Design Builder. The role involved oversight of the delivery of design review services, contract administration and dispute resolution advice.

Golden Ears Bridge
Confederation Line

The Golden Ears Bridge Project in the Greater Vancouver Area was a TransLink Public Private Partnership involving the design, construction and maintenance of a 976 m bridge over the Fraser River and 14 km of new roadway. The $800 million project was completed on budget and on time.

 

Tim Stanley acted as the Independent Certifier required by the Public Private Partnership Project Agreement. The role ultimately certified Substantial Performance and Total Completion. Tim led a team of professionals reviewing progress of the design and construction of the project to identify risks to certification early in the project execution to support a smooth process at the key milestones of Substantial Performance and Total Completion.

Ottawa’s new $2.2 billion Confederation Line transit system currently under construction consists of 13 stations along a new 12.5 km transit line. The alignment in many cases follows an existing Bus Rapid Transit facility and includes a new 2.5 km tunnel through rock under Ottawa’s downtown core. The project was completed in 2019.

 

Tim Stanley was instrumental in assembling the winning Public Private Partnership team and was the Partner in Charge for MMM Group (a 50/50 Design Joint Venture Partner with SNC Lavalin) during the project pursuit and design period. Tim was also a member of the Management Committee of the Design Joint Venture.

National Trade Centre at Exhibition Place

(Enercare Centre)

Columbia Power Corporation

This $180 million Design Build Project involved the development of a new Trade Centre in the heart of the City of Toronto. At over 1 million square feet this facility is Canada’s largest trade show space and opened in 1997.

 

Tim Stanley was the Deputy Project Manager on behalf of the Board of Exhibition Place and was responsible for the management of the development of procurement documents, indicative design and evaluation of proposals submitted. Key attributes to the selection of the successful team included Schedule, Price and Urban Design. Urban design was key due to the signature location of the facility.

Columbia Power
Corporation

Tim Stanley is the Past Chair of the Board of Columbia Power Corporation (a BC Crown Corporation). During his tenure at Columbia Power he was Chair of the Major Capital Projects (MCP) Committee. Under the oversight of the MCP Committee of the Board, Columbia Power completed the $900 million Waneta Expansion in Trail, BC. This 335 MW power plant was completed on budget and 6 weeks ahead of schedule.

Bruce Used Fuel Storage Facility

Lester B Pearson International Airport Redevelopment

Terminal 3 Expansion and Infield Development

This $100 million project involved the development of Radioactive WasteMaterial Processing Facility, Modification of the In-Station Used Fuel Bay, Procurement of a specialized vehicle to transport Used Fuel Containers and a Radioactive Waste Incinerator. 

 

Tim Stanley led a team of professionals to develop the procurement model, procurement documents and evaluation of proposals including the selection of the successful development team. The team also administrated the contract through to completion. Handling radioactive 

materials required specialized resources and processes within the Design Build contract.

Pitt River Bridge and Mary Hill Bypass Project

Bruce Used Fuel Dry Storage Project

This $180 million project involved the design and construction of a new cable stayed long 

span bridge (xxx m) and a new Lougheed Highway/Mary Hill Bypass interchange. Key 

challenges included weak and highly seismic sensitive soils along with the maintenance of 

high traffic volumes during construction. 

Tim Stanley was the Design Team Partner-in-Charge. The Design Team was under contract 

to Peter Kiewit and Sons, the Design-Builder for the project.

The Infield Development was a $300 million Design Build Project required to move existing land uses away from the planned expansion of the Passenger Terminal as a component of the $4.4 Billion redevelopment of Canada’s busiest airport. The Infield Development was designed to have a ten gate temporary passenger terminal (to provide swing space for the airport redevelopment), major cargo handling facilities, airport equipment maintainance facilities, a new hangar for wide body aircraft and Airline Catering Kitchens. The Design 

Build delivery was used to utilize its early development period schedule and cost certainty traits.

 

The $300 million expansion of Terminal 3 added substantial new gate capacity, expanded passenger processing capacity as well as high level security screening capabilities to the existing terminal developed in the late 1980s. This project utilized a series of design-bid-build 

contracts to complete the program of requirements.

 

For the Infield project, Tim Stanley, as the Project Manager led a team of Architects and Engineers to develop indicative designs, the procurement process as well as tender documents.

 

Mr. Stanley was the design team Project Manger for the Expansion of Terminal 3 and led  a team of Architects and Engineers to develop the project programme, preliminary designs and Tender/construction documents. He also led the evaluation and selection of the successful 

development/contractor teams. The team also

administrated the contracts through to completion.  Key to the success of this project was the provision of space that would be marketable and provide the expected revenue as outlined in the Authority’s business plan.

Port Mann Highway 1 Expansion​

IMG_4944.jpeg

Broadway Subway Project

This $2.4 billion Public Private Partnership project involved the design and construction of two large segments. The first segment was the replacement bridge over the Fraser River. The second segment was the “Onshore” works encompassing the expansion of Highway 1 including a total reconstruction of the Cape Horn interchange. The Onshore works were valued at $1.8 billion and included widening of active highway, numerous new bridges and retaining walls. Key challenges included weak and highly seismic sensitive soils along with 

the maintenance of high traffic volumes during

construction.

 

The Design Team was a Joint Venture of MMM Group and Hatch Mott MacDonald. Tim Stanley was the Partner-in-Charge for MMM Group and a key member of the Design Team Executive Management Committee. The Design Team was under contract to Peter Kiewit and Sons, the Design-Builder for the project.

The BC Ministry of Transportation and Infrastructure (MOTI) is delivering an extension of SkyTrain’s Millennium Line from VCC-Clark Station to a new terminus at Broadway and Arbutus Street, in Vancouver, British Columbia (BC). The $2.83 Billion, 5.7 kilometre Broadway Subway Project will include 700 metres of elevated track through False Creek Flats in Vancouver with the remaining Project Alignment being underground along the Broadway corridor towards the University of BC. The Project will add one new underground station at Great Northern Way, and five new underground stations along Broadway at Main, Cambie, Oak, Granville, and Arbutus streets to serve the important and growing Broadway Corridor.

 

An Owner Engineer Team led by Stantec is providing technical design services to develop the procurement documents as well as support the Province’s Team during the procurement period. Tim Stanley was contracted by Stantec to lead the Owner Engineer Team.

​

Stantec was also retained as the Independent Engineer upon the award of the Design Build Finance contract to the BSP Corporation team. Tim became the Independent Engineer through Stantec during project design, construction and commissioning.

proposed-george-massey-bridge-artist-ren

George Massey Replacement Project

Victoria WWT Plant.jpg

Core Area Wastewater Treatment Project

On September 20, 2013, Premier Clark announced that construction on a new bridge to replace the existing George Massey Tunnel will begin in 2017. On December 16, 2015, British Columbia Transportation Minister Todd Stone announced detailed plans to spend $3.5 billion on a bridge, highway widening and interchange improvements to replace the tunnel. In July 2016 the BC Environmental Assessment Office (EAO) started an environmental assessment of the project and on February 9, 2017 the replacement received environment approval from the B.C. Ministry of Environment. Preliminary work went out for tender in January 2017 to start the process of improving ground conditions for the future widening of the project area.

 

In early 2016 the procurement of a Public Private Partnership commenced, and Tim Stanley led the Design Team for one of the Proponents. This Proponent Team submitted a highly competitive proposal and was positioned to be the Preferred Proponent however with the election of a new provincial government in 2017, the NDP Premier John Horgan scrapped the project in favour of a solution with more research and consultation with the Metro Vancouver mayors. The potential Preferred Proponent Team was reported to be $900 million below the project budget.

The $775 million Wastewater Treatment Project will provide tertiary treatment for wastewater from the core area municipalities of Victoria, Esquimalt, Saanich, Oak Bay, View Royal, Langford and Colwood, and the Esquimalt and Songhees Nations. The Wastewater Treatment Project is being built to meet the provincial and federal regulations for treatment by December 31, 2020. The Project consists of three main components:

McLoughlin Point Wastewater Treatment Plant located at McLoughlin Point in Esquimalt, the treatment plant will provide tertiary treatment to the core area's wastewater.

Residuals Treatment Facility located at the Hartland Landfill  receives residual solids from the wastewater treatment plant by a forcemain. The facility will be turn the residual solids into what are known as Class A biosolids. These biosolids are a high-quality by-product treated such that it is safe for further use.

Conveyance System refers to the 'pumps and pipes' of the Wastewater Treatment Project. This system will carry wastewater from across the core area to the treatment plant, and residual solids to the Residuals Treatment Facility at Hartland Landfill.

Tim Stanley serves as a Director on the Project Board that oversees the implementation of the project.

PBR.jpg

Pattullo Bridge Replacement Project

Gordie Howe Bridge.jpg

Gordie Howe International Bridge Project

The existing Pattullo Bridge in British Columbia is a key connection between the communities of Surrey and New Westminster over the Fraser River. This key piece of infrastructure is at its end of life and is being replaced. The new $1.377 billion four-lane toll-free bridge will provide important improvements for everyone using the bridge, including people who are driving, cycling or walking including:

  • A safer crossing for all bridge users with modern, wider lanes, separated by a centre median barrier

  • Dedicated walking and cycling lanes, separated from traffic by a barrier on both sides of the bridge

  • Better connections to, from and near the bridge

The new bridge is scheduled to open in 2024. The existing bridge will remain in use until the new bridge is open to traffic. Once the new bridge is open, the existing bridge will be removed.

 

Tim Stanley is a member of the three person Due Diligence Committee (DDC)advising the Transportation Investment Corporation (a BC Provincial Crown Corporation) during the design and construction of this bridge project. The DDC monitors the ongoing progress of the project and provides critical advice on Budget, Schedule, Risk and Commercial management. The Transportation Investment Corporation is responsible for delivering and overseeing this large complex project.

The $6.4 billion Gordie  billion Gordie Howe International Bridge in Windsor, Ontario is a 6-lane cable-stayed bridge, 2.5 kilometres/ 1.5 miles in length with a clear span of 853 metres/0.53 miles. The bridge also incorporates a multi-use path for pedestrians and cyclists that is 3.6 metres/ 11.8 feet wide. The project includes new large Canadian Port of Entry and US Port of Entry facilities as well as connection to major highways on both sides of the border.

 

Once complete, the Gordie Howe International Bridge project will facilitate the movement of people, goods and services by ensuring there is sufficient border crossing capacity to handle growth in cross-border trade and traffic, by providing a much-needed crossing alternative. 

 

Tim Stanley is a member of the 3 person Dispute Resolution Board (DRB). Under the Project Agreement there is a dispute process that allows either party to the Agreement to refer a dispute to the DRB for review and decision. The DRB review involves assessment of written submissions from the parties and in some cases hearings. 

Building-FRTP_Step-8-1-1024x683.jpg

Fraser River Tunnel Project

 In Vancouver BC, after the cancelation of the Massey Tunnel Replacement Project (a new bridge plus highway upgrades)  in 2017, it was recognized that the existing tunnel required replacement and a new process to select the type of infrastructure was launched. The outcome of the study was the selection of a new larger immersed tunnel to replace the existing tunnel.

 

The proposed $4 billion Fraser River Tunnel Project includes a new, eight-lane immersed tube tunnel (780m) that will replace the existing George Massey Tunnel on Highway 99. The new tunnel will have three vehicle lanes and a dedicated transit lane in each direction, with a separated active transportation corridor for cyclists and pedestrians.  

​

The project also includes:

  • Replacing the Deas Slough Bridge

  • Removing the existing tunnel once the new immersed tube tunnel is in operation

 

Tim Stanley undertook a due diligence review of the Business Case for the new project which included a comparison of alternate types of infrastructure and an analysis of possible delivery approaches. Following this review Tim is providing procurement due diligence review services as well as broader project due diligence services.

bottom of page